Get involved in YOUR city and locality - Improve Your World
Get involved in YOUR city and locality - Improve Your World
Get involved in YOUR city and locality 
Improve Your World Home | About Us | Sitemap | Search | Contact Us 



Also see : Administrative Wards of Mumbai, Government Acts(By Topic), Government Schemes


Please help us in making this a comprehensive resource section for those directly connected or affected by this issue e.g. citizens, NGOs, government officers, students, teachers, researchers. Please directly upload or email us relevant content. This can include lists, articles, photographs, research papers, links to websites, etc. Please volunteer as an expert panelist to whom we can direct queries from our website visitors.

 

Home >> Mumbai Projects by Government >> City Transformation



Findstone.com - Marlet Place for Building Stones

A leap across the Arabian Sea: Mumbai's first big dream

Madhurima Nandy, Mumbai 

 

"There is no excuse for delaying a project. Across the world, there are penalties if you don't finish a project on schedule. There are several sealink projects in China, and there has been no delay."

 VICTOR CHEUNG Managing director, Halcrow Group, Shanghai

 

Building the Bandra-Worli Sealink is the experience of a lifetime. Chief Engineer Devendra Sharma

 

I T IS 8 am and the November sun is already strong. About 200 workers in blue hard-hats assemble on two windswept strips of concrete, resting on piers 94 feet above the Arabian Sea. Pinpoint information on today's tides along Mumbai's coasts has just arrived - from the Netherlands. Chief engineer Devendra Sharma and his team give a brief pep talk to the workers gathered from West Bengal, Orissa and Punjab as they prepare to build the soaring central tower - 45 storeys high that will hold in place the steel cables of the 5.6-km Bandra-Worli Sealink.

 

"THIS IS the experience of a lifetime," said Sharma, who works for Hindustan Construction Corporation (HCC), the project contractor. His last job: building an atomic power station in Rajasthan.

 

With technology from across the world and engineers from seven countries, India's first bridge across the sea is today little more than a shimmering mirage for frustrated commuters. They see it every day as they sit in vehicles stuck on the traffic-choked Mahim Causeway, a 1930s colonial-era bridge that is today the only link between Mumbai's sprawling, prosperous western suburbs and its southern business heart.

 

In a city that adds over 500 vehicles every day, the Sealink is the only hope for drivers who must cross 23 signals between Bandra and Worli. When it opens, it will carry 90,000 of the 1.30 lakh vehicles that now cross Mahim Causeway, promising to reduce a 40-minute crawl to a 7-minute high-speed ride - if it gets built by the end of 2008.

 

While Mumbai struggles to resolve squabbles over money between the state government and the contractor, China has built six sea bridges over the past five years. Another three are under construction. The 5-km-long Second Severn Crossing in the UK, with a 450-m-long cable-stayed main bridge, similar to the Bandra-Worli Sealink, was completed in four years. Another one in Denmark, the 7.5 km Oresund sea bridge, was functional in four-and-a-half years.

 

Conceived in the 1990s and contracted in 2000, the Bandra-Worli Sealink is already four years behind schedule but for Mumbai, this is the big one, the visible evidence of the Rs 43,000 crore makeover dream. For nearly 17 years, the state government has talked of a 20km-long Western Freeway, a ring of expressways skimming the western coast, including the Bandra-Worli Sealink and the Worli-Nariman Point Sealink, which is still on paper. The booming western seaboard is not just home to the newly prosperous but to the exploding middle-class and thousands of companies and people that drive the city's new economy: entertainment, infotech, finance.

 

Andrew Yeoward, senior project consultant with UK-based consultancy firm Halcrow Group, said China does sea bridges like no other country "There are no project delays in . China," Yeoward, who has been involved with several sea bridges across the world, told HT. "There is a lot of prestige attached with each project and completing them on time is a given."

 

The 7.6-km-long Sutong sea bridge is a perfect example of how quickly China executes projects. Built across the Yangtze river to connect the two prosperous cities of Suzhou and Nantong in eastern China, the Sutong bridge was completed in an extraordinary seven months.

 

On the global map, the Bandra-Worli Sealink is just another bridge across the sea. "There is no particular difficulty in building this sea bridge," said Yeoward. "There are many such bridges being built across the globe."

 

For Amit Wadhwa (30), a business analyst with a production house at Worli Naka, the incomplete Sealink is frustrating. "I spend at least 50 minutes going to work and an hour on my way home in the evening," said Wadhwa, who travels 20 km every day and spends nearly Rs 3,000 on fuel every month.

 

Wadhwa can't wait to use the sea route and wouldn't mind paying the expected daily toll of Rs 70. "The Sealink would cut down my travel time by more than half and the distance by nearly 6 km every day," he said.

 

Transport experts say the 80-year-old bridge - con crete, on stone pillars - across the 1.2-km-long Mahim Causeway, now needs to be rebuilt. The original Cause way was built in the 1840s to connect Mahim to Bandra, then part of the island of Salsette. In the 1930s, the Causeway was rebuilt into a bridge.

 

"Once the Bandra-Worli Sealink is built, the Mahim bridge can be rebuilt," said R.K. Jha, former managing director of the Maharashtra State Road Development Corporation. "A few years ago, the state government had thought of rebuilding the Mahim bridge but couldn't go ahead because it couldn't afford to block the stretch to traffic." Commuters on the rapidly gridlocking western link roads regard the Sealink as a magic wand. Many have noticed the Sealink's grand central tower rising above the concrete decks inching towards each other from north and south. Cables spiralling out of the tower will hold the main section of the deck in place. This is where the bridge is now stuck: cables need to be imported from China, and HCC says it has no money .

 

Nearly Rs 889 crore has already been spent on the project, more than double the original contract of Rs 400 crore. The contractor has received Rs 248 crore. "We need at least Rs 240 crore to begin the cable work on the main bridge from the Bandra end," said Ajit Gulabchand, Chairman of HCC.

 

The monsoon has receded and the sea is calm. Despite the squabbles, 2,500 workers have begun work around-the-clock. Mumbai can only hope they don't have to work beyond 2008.

 

madhurima.nandy@hindustantimes.com

 

The long and winding road

The project contract was signed on October 1, 2000, but the construction site at Bandra Reclamation was handed over to the contractor in May 2001.

 

NEW CONSULTANTS Sverdrup Consultants were appointed at the time of awarding of the project contract. Half way through in 2003, the state replaced them with Dar Consultants. Both are from the UK.

 

DESIGN CHANGES The basic design of the Sealink was changed after local fishermen protested. The Worli end was moved away from a fishing village, and the main Bandra cable-stayed bridge was changed from a single towered, eight-lane bridge to being double towered, with two four lane bridges.

 

MONEY SQUABBLE Contractor Hindustan Construction Company says it has already spent Rs 889 crore on the project but has received only Rs 248 crore from the Maharashtra government. The original project contract was for Rs 400 crore.

 

2003? NO. 2008? NO AGAIN! Initially, the project was to be completed by 2003. Then, it was extended till 2006-end. The new deadline is mid-2008, but that seems unrealistic. Expect a 2009 opening. 

Url: http://epaper.hindustantimes.com/default.aspx?selPg=1231&page=21_11_2007_010.jpg&ed=264