Electricity Issues : Important Dates of Public Hearings
Updated with REL and TPC data, on Feb 28th.
BEST, MahaGenco and MahaTransco Public Hearings are over. REL ATE hearing is over (Feb 20), matter still pending.
Here are the time-lines for MYT petitions:
1. MahaTransco (MSEB Transmission) Feb 6 - Petition for MYT Admitted (MERC Case No. 67 of 2006) Feb 8 - Public Notice in TOI Feb 23 - If public response submitted by this date, reply will be sent within 1 week. Feb 27 - Last date for Public response Feb 28 - Public Hearing at MERC, Mumbai Mar 5 - Last date for MahaTransco to file replies to public, if not already done, at hearing.
2. MahaGenco (MSEB Generation) Jan 31 - Petition for MYT Admitted (MERC Case No. 68 of 2006) Feb 6 - Public Notice in TOI Feb 19 - If public response submitted by this date, reply will be sent within 1 week. Feb 24 - Last date for Public response Feb 28 - Public Hearing at MERC, Mumbai Mar 5 - Last date for MahaGenco to file replies to public, if not already done, at hearing.
3. MahaVitaran (MSEB Distribution) Jan 31 - Petition for MYT Admitted (MERC Case No. 65 of 2006) Feb 11 - Public Notice in TOI Feb 26 - If public response submitted by this date, reply will be sent within 1 week. Mar 2 - Last date for Public response Mar 5 - Public Hearing at Amravati Mar 6 - Public Hearing at Nagpur Mar 9 - Public Hearing at Aurangabad Mar 12 - Public Hearing at Nashik Mar 14 - Public Hearing at Pune Mar 16 - Public Hearing at Navi Mumbai (for Mumbai residents also) Mar 10 - Last date for MahaVitaran to file replies to public, if not already done, at hearings. No mistake here, its Mar 10th only :)
4. BEST Jan 31 - Petition for MYT Admitted (MERC Case No. 66 of 2006) Feb 7 - Public Notice in Midday Feb 25 - Last date for Public response Feb 27 - Public Hearing at MERC, Mumbai
5. REL Jan 16 - Petition for REL-T MYT admitted Jan 22 - Petition for REL-G MYT admitted Jan 31 - Petition for REL-D MYT admitted Feb 25 - Public Notice in TOI Feb 26 - Copies available to Public Mar 15 - Last date for Public response Mar 19 - REL will give replies to public response (if filed by Mar 15) Mar 20 - Public can file rejoinders to REL's replies Mar 21 - Public Hearing at Vile Parle (E)
6. Tata Power Feb 26 - Petition for MYT admitted Feb 28 - Public Notice in TOI Mar 19 - REL will give replies to public response (if filed by Mar 13) Mar 19 - Last date for Public response Mar 20 - Public Hearing at IMC Hall, Opp Churchgate Station Mar 23 - Public can submit rejoinders (In case anyone notices any errors, email at snohri2004@yahoo.co.in). |